CLIENT:
"The Coca-Cola Company" Turkmenistan
PROJECT:
Reconstruction & Expansion of Coca Cola Factory
LOCATION:
Ashgabat / Turkmenistan
STATUS:
Completed
WORK SCOPE:
Engineering, Procurement, Fabrication, Construction
TYPE OF FACILITY:
Industrial Building / Factory
TOTAL FACILITY AREA:
20 000 m2
CONTRACT PERIOD:
8 month
CO2 SYSTEM HOUSE:
30T Cap, CO2 Condenser, 16-18 bar Generating Dehydration Unit, Evaporation Ion Unit 3800 kg/h
STEAM BOILER:
BOSCH Universal Steam boiler, temp: 300oC, 30 bar up to 18 000 to 55 000 kg/h
SYSTEM HOUSE:
Degasifire Tank 25 m3, Condensed Water Tank 16 m3, Fire Fighting: 7480 m2 sprinkler system, 15 fire hose cabinet, 150 m3 fire reserve tank
RAW WATER:
150 ton Water Tank, System Feed Pumps, filter backwash pumps
PIPELINES:
Up to 20ø-150ø, Avg Length: 3400 mt – galvanized pipeline, SS Pipeline, CS Pipeline, BS Pipelines, HDPE Pipeline, PVC/PPRC Pipeline
HVAC SYSTEM:
Galvanized steel air duck 8300 m2, 05-12 mm, Exhaust Fan: 22 000 m3/h, It 500 Pa, 3.1 kW, Rooftop Device 100 kw- 25 000 m3/h
FABRICATION:
Collectors: SS,BC, CS. Total Tonnage: 14 582 kg, Tankage: 7 no’s, Total Capacity: 12 ton
INSULATION:
34 000 m2 – rubber armaflex, rockwool, galvanized cladding